Check back here for progress updates and visuals from the sky of how everything is going with the project

 

NOVEMBER 2021

Demolishing existing houses commences

  • General site prep conducted

  • Removal of all existing structures on the property commences

DECEMBER 2021

  • bulk earthworks commences

  • Stormwater piping arrives on site

  • drainage basin created

JANUARY - FEBRUARY 2022

  • Brisbane floods tested the site, but the land pads, though incomplete remained flood free.

  • rectification works were in place to fix the damage caused, with minimal casualties to progress.

MARCH - APRIL 2022

  • Storm water management process commences through park area

  • remainder soil and top soil arrive on site.

  • Sewer piping installation commences.

MAY - JUNE 2022

  • Drainage installed into parkland area

  • Culvert drain installed in south precinct for stormwater drainage

  • Road cut commences.

JULY - AUGUST 2022

  • Retention basins removed from the estate

  • Majority of lots reach top level with compaction to follow

  • Road cut has commenced with majority of curb and channel installed on the north side.

SEPT - OCTOBER 2022

  • Park landscaping commence

  • Bitumen is done on the North and approved by council

  • final retaining walls are completed with earthworks closing off.

NOV - DECEMBER 2022

  • Completion of the estate

  • Roads finalised with plumbing and electrical works being activated

  • now awaiting registration.